DECISION SYSTEM
Site Qualification Scorecard
Edit weights and scores to test portfolio decisions in real time.
01 /
CRITERIA WEIGHTS
Available & expandable MWGATING
20%5 = 100+ MW | 3 = 40–79 MW | 1 = <20 MW
Time-to-energizationGATING
18%5 = <6 mo | 3 = 12–18 mo | 1 = >30 mo
Rack density readiness
12%5 = 130kW+ | 3 = 80–100kW | 1 = <40kW
Liquid-cooling readiness
12%5 = commissioned loop | 3 = designed | 1 = no path
Fiber & carrier diversity
11%5 = 3+ diverse | 3 = 2 planned | 1 = single route
Permitting & zoning risk
10%5 = by-right | 3 = routine hearing | 1 = contested
Incentives
7%5 = executed | 3 = indicative | 1 = unavailable
Financing / offtake fit
10%5 = fully aligned | 3 = term-sheet path | 1 = mismatch
02 /
LIVE RANKING MATRIX
| SITE | MW | TIME | DENSITY | COOLING | FIBER | PERMIT | INCENT. | FINANCE | SCORE | RECOMMENDATION |
|---|---|---|---|---|---|---|---|---|---|---|
Project MesquiteFICTIONAL | 95 | GO | ||||||||
Project AlderFICTIONAL | 93 | GO | ||||||||
Project IronwoodFICTIONAL | 85 | GO | ||||||||
Project JuniperFICTIONAL | 84 | GO | ||||||||
Project SaguaroFICTIONAL | 84 | GO | ||||||||
Project TamarackFICTIONAL | 81 | GO | ||||||||
Project BasaltFICTIONAL | 79 | GO | ||||||||
Project PrairieFICTIONAL | 72 | CONDITIONAL | ||||||||
Project CypressFICTIONAL | 72 | CONDITIONAL | ||||||||
Project GraniteFICTIONAL | 52 | NO-GO |