SHARED DEAL BOARD / PROJECT 01AS OF DEC 14, 2026
ONE DEAL · ONE SHARED RECORD
Project Red Mesa.
From commitment to compute. A shared place to keep every party aligned on what happens next.
Meridian Ridge CapitalFICTIONALRed Mesa Data Centers, DC-2FICTIONAL
THE BUILD576 GPUs
8 × Supermicro GB300 NVL72 racks
Hall A · Abilene-area, Texas
Shared board
01 / THE CURRENT PICTURE
Where things stand
The site is secured. Commercial terms are the next decision before financing can move forward.
GATE ACommercialJan 15, 2027
blockedB
GATE BCapitalFeb 12, 2027
not startedGATE CSite / coloPassed Nov 20, 2026
passedD
GATE DAcceptanceJul 9, 2027
not started02 / DELIVERY
From ship to service
SHIP DATE · SUPERMICROFri Jun 4, 2027
READY-FOR-SERVICE · RANGEJul 12 – Aug 2, 2027
SHIP ≠ RFSShip Jun 4 → Dock Jun 14 → Rack & stack Jun 15–25 → Burn-in Jun 28–Jul 5 → Acceptance Jul 9 → RFS Jul 12–Aug 2.
03 / WHAT'S NEXT
Upcoming milestones
Credit-support responseQuillfield response due
Commercial gateMSA + Order Form target
Hall A energizedSite readiness in writing
Hardware shipsNot ready for service
AcceptanceTest and sign-off target