DEAL BRIEF / PROJECT 01

Project Red Mesa

8 × Supermicro GB300 NVL72 racks · 576 GPUs · Hall A liquid cooling · Abilene-area, Texas

Meridian Ridge CapitalFICTIONAL→Quillfield Inference Co.FICTIONAL→Red Mesa Data Centers, DC-2FICTIONAL
pipeline
SHIP DATE · SUPERMICROFri Jun 4, 2027
READY-FOR-SERVICE · RANGEJul 12 – Aug 2, 2027
SHIP ≠ RFS
DELIVERY / CURRENT STATE

Deal at a glance

CAPACITY

576 GPUs

8 liquid-cooled GB300 NVL72 racks · ~135 kW/rack · ~1.1 MW IT load.

GATES

1 of 4 passed

Site / colo cleared Nov 20, 2026. Commercial remains blocked.

VIEWING AS

Hydra Internal

Internal deal overview.

01 / CRITICAL PATH

Gate status

GATE A / COMMERCIALblocked

MSA + Order Form signed; credit support agreed

TargetJan 15, 2027

Lender requires a 20% letter of credit from non-investment-grade offtakers. Quillfield won't post an LC. Proposal: 3-month prepay + parent guarantee; lender accepts at +100 bps. Awaiting Quillfield answer by Dec 18.

GATE B / CAPITALnot started

Financing committed

TargetFeb 12, 2027

If loan closes Feb 12 with 150-day longstop → Jul 12, 2027: the first day of the RFS window. Ask for Sep 30 or tie to Gate D.

GATE C / SITE / COLOpassed

Colo signed with energization dates in writing

TargetPassed Nov 20, 2026

Caught Oct 14: original offer was Hall B (80 kW/rack air). GB300 NVL72 needs ~135 kW liquid.

GATE D / ACCEPTANCEnot started

Acceptance certificate + lender verification

TargetJul 9, 2027

Acceptance thresholds still TBD in MSA.

02 / EXECUTION

Delivery phases

01Intake
02Commercial / offtake
03Capital
04Site / colo
05Procurement
06Logistics
07Build & acceptance
08RFS & operate
NEXT ACTIONS

Open work

T1 · Upload trailing-12-month financials for lenderDec 18
T2 · Respond to credit-support proposal (3-mo prepay + parent guarantee)Dec 18
T3 · Complete KYC/AML formsDec 22
T5 · Board sign-off on credit-support swapDec 21
T6 · Confirm prepay + guarantee meets credit box in writingDec 18
View action plan
SHARED RECORD

Latest decisions

3-mo prepay + parent guarantee instead of 20% LC; +100 bps accepted (Quillfield pending)Dec 10
Colo term = 3 years + 1 renewal (≥ offtake term)Nov 20
Hall B rejected; Hall A requiredOct 14
Decision log
03 / RECORDS

Documents

22 shared with this view
All documents