01
DECISION #1 · OCT 5, 2026

Path = spec cluster (no offtaker yet)

Decided by Meridian Ridge + Hydra

RECORDED
02
DECISION #2 · OCT 7, 2026

GB300 NVL72 over HGX B300: rack is the deployable unit

Decided by Investor + Hydra eng

RECORDED
03
DECISION #3 · OCT 9, 2026

Lead time 19 → 32 weeks; RFS moved to Jul 12–Aug 2, 2027

Decided by Hydra Procurement

RECORDED
04
DECISION #4 · OCT 14, 2026

Hall B rejected; Hall A required

Decided by FDE + colo

RECORDED
05
DECISION #5 · NOV 20, 2026

Colo term = 3 years + 1 renewal (≥ offtake term)

Decided by SPV + colo

RECORDED
06
DECISION #6 · DEC 10, 2026

3-mo prepay + parent guarantee instead of 20% LC; +100 bps accepted (Quillfield pending)

Decided by SPV, lender, Quillfield

RECORDED