STAKEHOLDER PORTAL / PROJECT RED MESA
Project Red Mesa — Colo / Data Center
Red Mesa Data Centers, DC-2FICTIONAL · L. Romero, Site Director
01 / MY NEXT STEP
Confirm CDU ownership + coolant spec
openDUE JAN 15
02 / WHAT WE NEED FROM YOU
2 open actions
T8Confirm CDU ownership + coolant spec
T9Countersign landlord / collateral-access waiver
03 / WHAT CHANGED
Since your last visit
DECISION #4
Hall B rejected; Hall A required
DECISION #5
Colo term = 3 years + 1 renewal (≥ offtake term)
ACTION PLAN
Your action plan
T8Confirm CDU ownership + coolant spec
Red Mesa Data Centers, DC-2 · Gate C
T9Countersign landlord / collateral-access waiver
Red Mesa Data Centers, DC-2 · Gate C
SHARED DEAL STATE
Deal status
GATE ACommercialblocked
GATE BCapitalnot started
GATE CSite / colopassed
GATE DAcceptancenot started
CONTACTS
Your contacts
Your teamL. Romero, Site Director
Hydra AI FactoryMatthew D., AI Factory lead
DELIVERY MILESTONES
Key dates
SHIP DATE · SUPERMICROFri Jun 4, 2027
READY-FOR-SERVICE · RANGEJul 12 – Aug 2, 2027
SHIP ≠ RFSShip Jun 4 → Dock Jun 14 → Rack & stack Jun 15–25 → Burn-in Jun 28–Jul 5 → Acceptance Jul 9 → RFS Jul 12–Aug 2.
SITE / HALL A
Facility readiness
Energization / CDU commissioningApr 30, 2027
Dock windowJun 14, 2027
FDE crewJun 15–25
8 liquid-cooled GB300 NVL72 racks · ~135 kW/rack · ~1.1 MW IT load. Hall B air cooling (80 kW/rack) was rejected.