STAKEHOLDER PORTAL / PROJECT RED MESA
Project Red Mesa — OEM / Procurement
Supermicro · Supermicro account team
01 / MY NEXT STEP
Confirm ship date per PO line incl. optics, switches, CDUs
overdueDUE DEC 15
02 / WHAT WE NEED FROM YOU
2 open actions
T10Confirm ship date per PO line incl. optics, switches, CDUs
T11Confirm NVIDIA allocation letter
03 / WHAT CHANGED
Since your last visit
DECISION #2
GB300 NVL72 over HGX B300: rack is the deployable unit
DECISION #3
Lead time 19 → 32 weeks; RFS moved to Jul 12–Aug 2, 2027
ACTION PLAN
Your action plan
T10Confirm ship date per PO line incl. optics, switches, CDUs
Supermicro · Gate —
T11Confirm NVIDIA allocation letter
Supermicro · Gate —
SHARED DEAL STATE
Deal status
GATE ACommercialblocked
GATE BCapitalnot started
GATE CSite / colopassed
GATE DAcceptancenot started
CONTACTS
Your contacts
Your teamSupermicro account team
Hydra AI FactoryMatthew D., AI Factory lead
DELIVERY MILESTONES
Key dates
SHIP DATE · SUPERMICROFri Jun 4, 2027
READY-FOR-SERVICE · RANGEJul 12 – Aug 2, 2027
SHIP ≠ RFSShip Jun 4 → Dock Jun 14 → Rack & stack Jun 15–25 → Burn-in Jun 28–Jul 5 → Acceptance Jul 9 → RFS Jul 12–Aug 2.
PO #SMC-RM-1023 / DELIVERY
Purchase order lines
GB300 NVL72 rack ×8Jun 4, 2027
800G opticsTBD
Quantum-X800 IB switchesTBD
CDUsTBD
Deliver to Red Mesa DC-2, Hall A dock (fictional) · dock window Jun 14, 2027.
SHARED REPOSITORY
Your documents
Hidden from this view: Offtake, financing, fees, colo pricing.